What simply occurred? Intel introduced a big revision to the development timeline of its Ohio One semiconductor manufacturing web site in New Albany. The setback is the third substantial delay from the ability’s authentic 2025 completion goal. Intel emphasizes its dedication to the undertaking and its capability to speed up development if market demand warrants.
The primary section of the ability, often called Mod 1, needs to be completed in 2030, with chip manufacturing starting between 2030 and 2031. The corporate’s revised timeline additionally impacts the undertaking’s second section, Mod 2, pushing it again to a 2031 completion date, with operations starting in 2032.
The Ohio One campus, as soon as dubbed the “Silicon Heartland,” is an formidable enterprise. It should span roughly 1,000 acres and embody as much as eight semiconductor fabrication vegetation. The location may even accommodate assist operations and trade companions. Preliminary funding estimates had been round $20 billion, with potential for as much as $100 billion in complete growth prices.
Regardless of the frequent delays, the location has made vital development progress since work started in 2022. Key milestones embody completion of the underground basis, graduation of above-ground development, set up of air separation models and underground piping, pouring over 200,000 cubic yards of concrete, and greater than 6.4 million hours of invested labor.
The revised timeline reveals that the Ohio amenities will make the most of course of applied sciences developed after Intel’s 14A and 14A-E nodes, at the moment scheduled for introduction in 2026-2027. These superior manufacturing processes will possible depend on ASML’s cutting-edge Excessive-NA EUV lithography instruments, costing round $350 million every.
Intel has already begun hiring and coaching staff for the Ohio facility. Employees are receiving coaching at current Intel websites in Arizona, New Mexico, and Oregon, getting ready them for the eventual opening of the native facility.
Intel’s resolution to delay the Ohio plant opening comes amid a difficult interval for the corporate and the semiconductor trade. The previous yr has seen Intel grappling with monetary losses, layoffs, and management modifications. The corporate has additionally made strategic selections to simplify its product roadmap, together with canceling an AI chip undertaking.
Whereas the delay could elevate considerations about Intel’s outlook on future demand, it additionally permits the corporate to handle its capital expenditures extra successfully throughout market uncertainty. By suspending vital investments in manufacturing tools, Intel can deal with returning to profitability whereas sustaining the flexibleness to ramp up operations when market circumstances enhance.